Technical requirements for a car wash
Water supply, electricity supply and a prepared construction site are prerequisites for installing the equipment. Connection planning data and works to be prepared before assembly are collected here.
Connections according to the number of washing places
Use the table for the initial evaluation of the object. The final connection solution is determined by the technical documentation of the chosen system and project calculations.
| Baysfor washing | Waterm³/h | P₁kW | IₙA |
|---|---|---|---|
| 2 | 1,7 | 12 | 30 |
| 3 | 2,3 | 15 | 35 |
| 4 | 3,4 | 23 | 63 |
| 5 | 4,0 | 26 | 63 |
| 6 | 5,1 | 34 | 100 |
| 7 | 5,8 | 37 | 100 |
| 8 | 6,5 | 42 | 100 |
P₁ — electric power specified by the manufacturer; Iₙ - connection current specified in the document. These values are not a ready-made selection table for cables or protective devices.
The table summarizes the basic CarWash data specified in the manufacturer's documentation for initial planning. They do not replace the technical specification of the selected system. Parameters of WashTerminal, electric water heating and other configurations are specified separately.
Water supply pressure; not lower than 3.0 bar during flow.
Three-phase power supply. The connection scheme is determined by the selected equipment and electrical project.
Water supply and sewage
- The water supply must provide the supply flow specified in the table at the required pressure.
- Manufacturer's requirement: supply pressure 4-6 bar, minimum flow pressure 3.0 bar.
- Water and sewer connections must be completed and accessible before assembly.
- The collection and treatment of wastewater from the washing areas, including the separator of oil products, must be provided in accordance with the project of the facility and the technical regulations of the network operator.
- The connection and cleaning solution is coordinated with the designer, observing the requirements applicable to the object and the manufacturer's documentation.
In the manufacturer's documentation for separators, there is a reference to DIN 1999. The set of standards applicable in Latvia and the specific solution are determined within the project; The DIN reference is not a universal substitute for all local requirements.
Power supply, cables and protection
- For the basic CarWash system, the document specifies a three-phase 400 V / 50 Hz power supply.
- The electrical project must take into account the power and current of the selected washing system, as well as additional equipment, lighting, heating and other consumers of the object.
- The number of cable cores, material and cross-section, protection devices and connection solution are chosen by the electrical designer according to the equipment documentation and construction conditions.
- The length of the cable route, the type of laying, the load, the voltage drop and the protection conditions must be evaluated.
- Electrical connections and tests are performed by appropriately qualified specialists.
Separately - power supply for assembly works
During assembly, water and at least 230 V electricity supply with 16 A protection with delay must be provided in the object, as specified in the manufacturer's document. This is an assembly requirement, not a service connection for the entire car wash.
Cross-sections of copper wire strands
Asynchronous motor connection reference table with copper (Cu) conductor cross-sections.
| Motor powerkW | Motor rated currentA | Cross section of copper wiremm² |
|---|---|---|
| 1,0 | 2,2 | 1,5 |
| 1,5 | 3,22 | 1,5 |
| 2,2 | 4,95 | 1,5 |
| 3,0 | 6,1 | 1,5 |
| 4,0 | 8,0 | 1,5 |
| 4,5 | 10,0 | 2,5 |
| 7,0 | 14,0 | 2,5 |
| 10,0 | 19,6 | 2,5 |
| 13,0 | 24,8 | 4 |
| 17,0 | 32,0 | 6 |
| 20,0 | 42,0 | 10 |
| 23,0 | 43,0 | 10 |
| 28,0 | 55,0 | 16 |
| 30,0 | 56,0 | 16 |
| 40,0 | 74,0 | 25 |
Preparation of construction site and building structures
- The customer organizes the necessary project documentation, approvals and permits, unless otherwise stipulated in the contract.
- There must be developed solutions for architecture and building structures, calculations of the bearing capacity of metal structures and plans for the reinforcement of concrete slabs in the washing areas.
- Before assembling the equipment, the necessary masonry, concreting, foundation and drainage works must be completed.
- The scope of construction works and connections, as well as the division of responsibility, is coordinated in the project and the contract.
- Free access for delivery and assembly equipment must be provided on a prepared, load-bearing surface.
Technical room, heating and frost protection
- If the technological modules are installed in a container or building, the space must be sufficient for the placement and maintenance of the equipment.
- Adequate ventilation, frost protection and a sink should be provided.
- During assembly, the technical module or room must be heated in winter to prevent frost damage.
- The gas or fuel supply of the burner is designed according to the requirements of the manufacturer of the selected heating equipment.
- Insulation of pipelines, additional heating and start-up of systems are carried out by specialists qualified for the relevant work.
- The type and required amount of heat carrier of the heating system are specified in the technical documentation of the specific project.
Delivery, assembly and first start-up
For unloading - loader or crane
The manufacturer's requirement provides for a forklift in the facility with at least 3.75 m lifting height or a suitable crane. Lifting capacity and access are specified according to the mass of the equipment to be delivered and the unloading plan.
3.75 m is the lifting height of the forklift, not a universal requirement for the height of the room or wash box.
- The start of assembly is coordinated after the construction works are completed and the necessary connections are prepared.
- Ensures smooth progress of works at the facility and coordinates the work of other contractors.
- All water, sewer, electrical, gas or fuel connections for the selected system must be completed prior to first start-up.
- Additional sections of high-pressure pipelines and non-standard solutions in existing buildings are coordinated with EHRLE and included in the scope of the project.
- Built-in parts, such as control terminal frames, are coordinated with EHRLE in time. The manufacturer's assembly conditions specify ordering at least two weeks before the planned assembly; actual delivery terms are specified separately.
Information updated on 03.11.2026. Basis: EHRLE technical data and manufacturer's 2026 assembly conditions; copper wiring table - connection reference data for induction motors. Project-specific approved documentation takes precedence over this review.
